In 2007, we carried out the Installation of the CMRP SKID, carried out the complete installation of the set of valves at the Brumadinho Gas Receiving Station.
ABOUT THE WORK
Executed City-Gate with cathodic protection, odor dispersion system, lighting and lightning protection system and special crossing works, and crossings by Non-Destructive Method (MND) in a stream (100.00 m), in Lagoa das Codornas (120, 00 m) and intersections of BR-040 (80m), BR 356 (160.00 m).
Diameter: 10″
Length: 33,278 meters
Material: API 5L Grade B Steel
Non-Destructive Method (NDM)
CLIENT: GASMIG SEGMENT: GAS PIPELINE LOCATION: BRUMADINHO NOVA LIMA/MG