The Elevação Construction carried out the work for the use of BioGás – carried out with reduced environmental impact, greater safety, and great agility.
ABOUT THE WORK
In 2017, Elevação started the Polyamide work in Caucaia. Manual excavation in the open field in rock with explosives, manual drilling up to 2m – 379.43m³, excavation load transport 3rd category 4001 to 5000m – 699.38m³. Construction of a GNR custody transfer station and Construction CRM – CERBRAS. The use of Polyamide resulted in a safer, faster work, with less environmental impact and for a lower total investment.
WORK HIGHLIGHTS
● Customer CEGÁS won the Regional Innovation Award for the work. ● 23 km of gas pipeline built with innovative Polyamide technology. ● The Largest Polyamide 12 gas pipeline in the world for the use of Biomethane. ● Use and consumption of Renewable Natural Gas produced from garbage. ● Work entirely carried out using a directional hole – non-destructive method. ● Technology that facilitates the facilitation of environmental licenses, increases safety at work and reduces delivery times. ● Diameter: 160mm ● Material: Polyamide PA U12-180, SDR-11. ● Non-Destructive Method (MND): 20,125 meters.
CLIENT: CEGÁS SEGMENT: GAS PIPELINE LOCATION: CAUCAIA/CE